The BLV Group operators are currently repositioning two plants located on the westerly side of the site and will commence operations shortly. These plants are expected to operate until winter conditions arrive.
We have recently started an external gravel haul in March from Phase 5 East located adjacent to 85 Street to an alternate site on the opposite side of 85 Street. This haul will supply offsite crushing
The BLV Group is scheduled to conduct a small routine blasting operation on the western side of the pit in the near future (Tuesday February 13th) between Noon and 5pm. Blasting is a safe permitted ac
We will be starting earthmoving activity this week (weather dependant) in Phase 5 East located adjacent to 85 Street utilizing scrapers and dozers. The activity will remove overburden to expose the gr