Earthmoving Activity

  • Stoney Trail Pit
  • Mar 25, 2020
  • 1 min read

We have started earthmoving activities in a new area of the pit located just north of the powerlines in the center of the site. It will be daytime hours only for a couple of weeks. One of the crushers located near this earthwork is not producing during this time but will resume once the earthmoving is complete.

 
 
 

Recent Posts

See All
Blast Notice - Friday, November 7, 2025

The BLV Group is scheduled to conduct a small routine blasting operation on the Eastern side of the pit on Friday, November 7th between Noon and 5pm. Blasting is a safe permitted activity and will onl

 
 
 
Earthmoving Activity - Western Program

W e will be starting earthmoving activity this week in Phase 5 West located towards the Western sound berm utilizing scrapers and dozers. The activity will remove overburden to expose the gravel depos

 
 
 