top of page
Search
  • Writer's pictureCurtis KLINGER

85th Street Crossing: External Gravel Haul

We have recently started an external gravel haul in March from Phase 5 East located adjacent to 85 Street to an alternate site on the opposite side of 85 Street.


This haul will supply offsite crushing of material at alternate locations to reduce the amount of material processed in pit compared to 2023. This haul is expected to be conducted over the next three months with the aim to be completed by early June 2024.


Temporary crossing lights have been installed on 85 Street to ensure the safety of local traffic and are operated manually to minimize wait times between truck crossings.

4 views0 comments

Recent Posts

See All

Stantec Surveying Along STAR Site Perimeter

Stantec is expected to conduct surveying activities for the City of Calgary along the Western and Northern borders of the STAR site adjacent to both Rocky Ridge Road NW & 144 Ave NW respectively. The

STAR Pit Activity Update

The BLV Group operators are setting up an additional crushing plant located on the eastern half of the STAR site towards 85 Street. This plant will provide resources to support the Alberta Government'

85th Street Crossing: External Gravel Haul Update #1

Starting Monday April 15th, the current external gravel haul will commence a 24 hour running cycle. This change in schedule aims to reduce the overall duration of the truck crossing. Temporary crossin

bottom of page