85th Street Crossing: External Gravel Haul Update #1

Writer: Curtis KLINGERCurtis KLINGER

Starting Monday April 15th, the current external gravel haul will commence a 24 hour running cycle. This change in schedule aims to reduce the overall duration of the truck crossing.


Temporary crossing lights will be staffed throughout all hours to continue to ensure safety of local traffic and minimize wait times between truck crossings.

 
 
 

Recent Posts

See All

STAR Pit Activity Update

The BLV Group is moving a pre-existing crusher West to a temporary location to capitalize on crushing requirements for the Western side...