The small road base plant that was utilized to assist with increased City of Calgary demand has completed its duties and has been shipped out of the STAR site.
The BLV group has begin paving work at the front entrance of the STAR site that is expected to be completed in early May. This project will refresh existing asphalt while also doubling the size of the
An Alberta Transportation Contractor anticipates to start utilizing the same 2025 portable asphalt plant in the STAR Site. Its location will remain in the South-East corner adjacent to 85th Street NW.
The BLV Group is scheduled to conduct a small routine blasting operation on the Eastern side of the pit on Friday, March 6th between Noon and 5pm. Blasting is a safe permitted activity and will only b
Comments