Chain Link Fencing

The BLV Group has commenced extending the site's chain link fence to enclose Phase 4 & 5.


Work has begun behind the new enhanced berm along Rocky Ridge Road by the Altalink Powerline. The new fence will proceed northward to approximately the quarter section line and then will head east across the site to 85th Street and then tie to the existing chain link south in Phase 3.


We are working with the U of C Vet School on additional farm fencing required inside the chain link for their continued grazing of livestock on the lands.


We expect this work to take several weeks.

10 views0 comments

Recent Posts

See All

STAR Pit Activity Update

The BLV Group operators are setting up an additional crushing plant located on the eastern half of the STAR site towards 85 Street. This plant will provide resources to support the Alberta Government'

85th Street Crossing: External Gravel Haul Update #1

Starting Monday April 15th, the current external gravel haul will commence a 24 hour running cycle. This change in schedule aims to reduce the overall duration of the truck crossing. Temporary crossin

STAR Pit Activity Update

The BLV Group operators are currently repositioning one washing plant located from the southern border of the STAR site to the eastern side of the STAR site adjacent to the 85 Street truck crossing. T