Blasting Activity

We will be conducting a small routine blasting operation on Thursday July 2nd between Noon and 5pm in the Phase 3 East area of the pit. Although not likely, you may hear the sound of distant thunder and feel a faint thump if your in the vicinity


3 views0 comments

Recent Posts

See All

STAR Pit Activity Update

The BLV Group operators are currently repositioning two plants located on the westerly side of the site and will commence operations shortly. These plants are expected to operate until winter conditio

Earthmoving Activity

We will be starting earthmoving activity this week in Ph 3 East located adjacent to 85 Street utilizing scrapers and dozers. The activity will remove overburden to expose the gravel deposit and place