85th Street Crossing: External Gravel Haul Update #2

  • Writer: Curtis KLINGER
    Curtis KLINGER
  • Jun 6, 2024
  • 1 min read

While the May rainfall has been great for our greenery - wet conditions slowed down the external gravel haul.


In response, a three week extension (12 working days) is to occur to ensure the project can reach completion. During this time, the operation will continue their daytime running cycle. Temporary crossing lights will also continue to be staffed throughout running hours to ensure safety of local traffic and minimize wait times between truck crossings.

 
 
 

Recent Posts

See All
Front Entrance Paving Program

The BLV group has begin paving work at the front entrance of the STAR site that is expected to be completed in early May. This project will refresh existing asphalt while also doubling the size of the

 
 
 
Blast Notice - Friday March 6, 2026

The BLV Group is scheduled to conduct a small routine blasting operation on the Eastern side of the pit on Friday, March 6th between Noon and 5pm. Blasting is a safe permitted activity and will only b

 
 
 

Comments


bottom of page