top of page
Search

85th Street Crossing: External Gravel Haul Update #2

Writer: Curtis KLINGERCurtis KLINGER

While the May rainfall has been great for our greenery - wet conditions slowed down the external gravel haul.


In response, a three week extension (12 working days) is to occur to ensure the project can reach completion. During this time, the operation will continue their daytime running cycle. Temporary crossing lights will also continue to be staffed throughout running hours to ensure safety of local traffic and minimize wait times between truck crossings.

 
 
 

Recent Posts

See All

STAR Pit Activity Update

The BLV Group is moving a pre-existing crusher West to a temporary location to capitalize on crushing requirements for the Western side...

Comments


© 2020 by BOJAX DIGITAL SOLUTIONS

bottom of page